Teardown

Energy · Deep dive

Helion Energy

Silicon Valley's single most-funded bet on commercial fusion, with a signed Microsoft PPA for 50 MW in 2028 and a $5.4B valuation.

emerging

The question that decides it: Does Polaris or Orion demonstrate net electricity before the Microsoft 2028 deadline (or a credible path that keeps Series G capital flowing)?

My take

Founded
2013
Headcount
500
Screen
Published
2026-11-24
Web
www.helionenergy.com
Elsewhere
LinkedIn · Crunchbase

Founders and leadership

  • David Kirtley Co-founder & CEO

    Plasma physicist; co-authored University of Washington inductive plasmoid accelerator (IPA) research with Slough

  • John Slough Co-founder

    University of Washington Redmond Plasma Physics Lab; principal investigator on the IPA experiments (2005-2012) that are Helion's IP lineage

  • Chris Pihl Co-founder & CTO

    Plasma engineer; co-authored IPA papers with Slough

  • George Votroubek Co-founder & Principal Scientist

    Plasma researcher; co-authored IPA papers with Slough

Snapshot

Helion Energy is the fusion company that has gone furthest in selling electricity before producing it. Founded in 2013 and headquartered in Everett, Washington, it raised a $425M Series F in January 2025, bringing its valuation to $5.4B and cumulative equity raised to the north of $1B when government and milestone funds are included. Its signature deal, announced May 2023, is a power purchase agreement with Microsoft for 50 MW of electricity starting in 2028 — the first commercial PPA ever signed for fusion power, and one most of the fusion community publicly doubts can be met. Helion is pursuing a magneto-inertial fusion approach using deuterium and helium-3 fuel; its seventh prototype, Polaris, completed construction at the end of 2024 and reported hitting 150 million °C in February 2026. The company's position in the fusion race is that of the single bet most explicitly funded by Silicon Valley, with Sam Altman as chair and the largest personal investor, and the bet most exposed to a Microsoft counterparty with unlimited patience if the technical story stays plausible.

Founding story

Helion grew out of plasma physics work by John Slough at the University of Washington Redmond Plasma Physics Lab. Slough co-founded the company in 2013 with David Kirtley (now CEO), Chris Pihl (CTO), and George Votroubek (principal scientist). The IP lineage is the inductive plasmoid accelerator experiments Slough's group ran from 2005 to 2012. Helion was a 2013 Clean Tech Open finalist, participated in Y Combinator (the record is inconsistent — both 2013 and 2015 are referenced), and received an ARPA-E ALPHA contract in 2015. Mithril Capital led the first meaningful private round in 2014 at $1.5M; early government support totalled around $7M from NASA, DOE, and DoD. The company existed on fumes for the better part of a decade before Sam Altman wrote a $375M personal cheque into the November 2021 Series E, anchoring the Silicon Valley thesis that fusion was finally close.

How it works

Helion's reactor is linear, not toroidal. It fires two field-reversed configuration (FRC) plasmas from opposite ends of a chamber at ~300 km/s, compresses them together using pulsed magnetic fields, holds them at fusion conditions for microseconds, and uses the plasma's own expansion against the magnetic field to directly recover electricity — bypassing the steam turbine step that tokamak-based designs still rely on. The fuel is deuterium combined with helium-3, a choice that reduces the neutron flux problem but creates a severe fuel-supply problem: terrestrial helium-3 is so scarce that Helion is working on breeding it from D-D side reactions. A commercial reactor is designed to pulse approximately once per second, with each pulse producing a small amount of electricity that integrates to continuous output. The Polaris prototype, completed end of 2024 and reported by Helion to have reached 150 million °C in February 2026, is designed to demonstrate electricity generation (not yet net) from a D-T reaction before Helion moves to the next prototype, Orion. The Microsoft PPA covers the generation stage after Orion.

Product and business overview

  • Fusion reactor system. Linear FRC compression device, pulsed magnetic, direct electricity extraction.
  • Deuterium + helium-3 fuel path. Includes a planned helium-3 production module (from D-D side reactions) because terrestrial supply is insufficient.
  • 50 MW commercial plant (planned). Announced in July 2025 near Malaga in Chelan County, Washington, on land owned by the Rock Island Dam PUD, intended to supply Microsoft data centres beginning in 2028.
  • Prototype pipeline. Polaris (seventh, completed 2024), Orion (eighth, under design), each ~25-100% larger than the previous.

Business model and pricing

Helion sells electricity via long-term PPAs to hyperscalers and (eventually) utilities, with an undisclosed price per MWh in the Microsoft deal. Industry speculation puts the contracted rate at the high end of long-term clean-firm power — perhaps in the $80-$150/MWh range — materially above commercial solar PPAs but potentially in range of new-build nuclear SMRs. The strategic value to Microsoft is not the price; it is the option value of clean, dispatchable, non-intermittent power inside a hyperscaler's own PPA book. Helion's revenue until 2028 is effectively zero.

Traction over time

Date Milestone
2013 Founded (Slough, Kirtley, Pihl, Votroubek).
2014 $1.5M private seed (Y Combinator, Mithril Capital).
2015 ARPA-E ALPHA contract; ~$7M early government funding, per Wikipedia.
Nov 2021 $500M Series E led by Sam Altman, $3B valuation; up to $1.7B in milestone commitments, per Bloomberg.
May 2023 50 MW PPA signed with Microsoft for 2028 delivery, per CNBC.
End 2024 Seventh prototype Polaris construction completed, per NEI.
Jan 2025 $425M Series F; $5.4B valuation; Nucor, Lightspeed, SoftBank Vision Fund 2 among investors, per TechCrunch.
May 2025 Washington HB 1018 signed, classifying fusion as clean energy.
Jul 2025 50 MW Malaga plant announced near Rock Island Dam, Chelan County, per Helion.
Feb 2026 Reported 150 million °C D-T fusion on Polaris, per Helion.
2025 Headcount 500+, per Wikipedia.

Market analysis

The near-term TAM is not "the electricity market". It is the clean-firm power sub-segment hyperscalers are willing to pay a premium for because they have signed net-zero data centre commitments and do not want to rely on intermittent renewables plus batteries alone. Rystad estimated global hyperscaler power demand at ~90 TWh in 2024 and projects a 3-4x increase by 2030 (Rystad, Sep 2024). The IEA's World Energy Outlook 2024 projects global fusion R&D spending topping $7B/year across public and private sources by mid-decade. The structural force is a genuine capacity shortage: PJM, ERCOT, and MISO queue delays average 3-5 years for interconnection; new nuclear SMR delivery dates have slipped to the 2030s. If Helion ships even a single working 50 MW module by the end of the decade, it jumps every other clean-firm option in the queue.

Competitive intel

  • Commonwealth Fusion Systems — Bain Capital-backed, MIT spinout, $2B+ raised through 2024, tokamak with high-temperature superconducting magnets, planning SPARC demonstration in 2026-27. Closest commercial rival on timeline and the one real competitor for hyperscaler PPAs.
  • TAE Technologies — $1.2B+ raised, hydrogen-boron (p-B11) fuel, Orange County-based. Longer timeline but alternative fuel path that avoids helium-3.
  • Tokamak Energy — UK, spherical tokamak with HTS magnets, raised ~$250M.
  • Zap Energy — Seattle neighbour, Z-pinch approach, raised ~$327M.
  • General Fusion — Jeff Bezos-backed, magnetised target fusion, raised ~$440M total but hit a funding crunch and material layoffs in 2025.
  • Government programs — ITER (France) and the US DOE National Ignition Facility are not commercial but set expectations around feasibility and cost. NIF's December 2022 ignition result changed the political weather.

History and evolution

Helion's history is a long technical slog (2013-2020) followed by a sudden capital shift (2021-2025) catalysed by Sam Altman. The Microsoft PPA is the pivot point of the company's narrative: it converted Helion from one of several Silicon Valley fusion bets into the fusion company with a contract. The 2024-2026 trajectory has been milestone-by-milestone on Polaris, with the headline achievements — 150 million °C in Feb 2026 — publicly announced but not yet independently verified or peer-reviewed. The stumbles include a widely noted miss on the original 2024 "net electricity" goal Kirtley cited to Bloomberg in late 2021, and the ongoing industry scepticism around the D-He3 fuel supply.

What people say

The case for. Technical peers acknowledge Helion's pulse rate and direct energy conversion approach as the most pragmatic path to a usable electricity output among private fusion plays. Altman, Peter Thiel, and the Series F syndicate of Nucor, Lightspeed, and SoftBank Vision Fund 2 are the clearest endorsement; Nucor in particular is strategic because steel is one of the largest industrial power consumers and clean-firm power is an unsolved problem for electric arc furnaces. Washington State's May 2025 fusion-is-clean legislation removes the local permitting risk at Malaga.

The complaints. Fusion physicist Daniel Jassby's 2019 critique grouped Helion with what he termed "voodoo fusion"; a 2018 MITRE/JASON report identified plasma stability as a core unsolved problem for FRC approaches. More recently, the Register and IEEE Spectrum have pointed out that no FRC device has ever produced net electricity, that He-3 supply is unresolved, and that Helion's own public milestones have slipped relative to Kirtley's 2021 statements. The Microsoft PPA has been publicly characterised by multiple industry analysts as effectively an option contract — Microsoft takes power if Helion delivers, pays nothing if not — rather than a genuine commercial commitment. The Series F valuation of $5.4B therefore prices in a probability of commercial fusion by 2028 that most practitioners outside Helion put in single digits.

Outlook: the open question

Does Polaris demonstrate net electricity before the Microsoft 2028 deadline, or at minimum a credible path to it that keeps Series G capital flowing? The answer decides whether Helion is the next Space Technology Hyperloop (a Silicon Valley bet that never shipped) or the SpaceX of the fusion sector. If Helion generates net electricity on Polaris or Orion by 2027, the Malaga plant becomes real, the Microsoft deal survives, and Helion raises a growth round at a higher valuation that lets it build a commercial-scale reactor. If Helion misses — repeatedly, publicly, and without a net-energy result — the Microsoft deal lapses, the Series F investors absorb a markdown, and Helion either pivots to a research-contract business or winds down. The intermediate answer Helion will actually deliver is a sequence of partial results on Polaris and then Orion: temperature milestones, pulse-repetition milestones, direct electricity recovery milestones. Each one buys more capital. Whether any of them add up to a commercial reactor is a physics question that will only be settled by Polaris and Orion data.

How to attack it

A new entrant has limited room to attack Helion head-on on fusion — the capital barrier is too high and the physics risk too long-dated. The practical attack vectors sit in the adjacent layers. First, clean-firm power aggregation and PPA structuring. Helion's 50 MW PPA is a thin slice of what hyperscalers will buy; a startup that aggregates clean-firm supply (geothermal, SMR, hydrogen, enhanced geothermal, next-gen nuclear) into a single hyperscaler-ready contract becomes the counterparty hyperscalers prefer to any single technology. Fervo Energy, X-energy, and Oklo have already begun this; the aggregator layer is still unbuilt. Second, helium-3 supply. If Helion is right about the fuel pathway, He-3 is a bottleneck worth a company; a startup focused on He-3 breeding reactors or lunar He-3 extraction is a credible pick-and-shovel bet. Third, direct energy conversion components — the high-current switches, the capacitor banks, the superconducting bus bars — are shared across most fusion architectures and are supply-constrained today. Helion's weaknesses to exploit: its fuel pathway is scientifically contested; its 2028 timeline is implausible to most of the physics community, which creates headline risk that compounds if Microsoft walks; its direct energy recovery claim has not been independently measured; and its competitive moat against Commonwealth Fusion Systems is not technological but temporal — CFS has more academic credibility, Helion has an earlier contract. A well-funded tokamak competitor with a nearer-term SPARC demonstration (CFS's actual 2026-27 plan) could re-order the industry narrative overnight.

Adjacent-segment play

Helion's underlying capability stack — ultra-high-current pulsed power electronics, field-reversed plasma physics, and direct energy conversion — generalises to markets other than grid electricity. Directed energy (defence) is the most obvious adjacency: the US DoD has spent heavily on high-power microwave and railgun programs that use similar pulsed-power infrastructure. Industrial process heat is the biggest potential: steel, cement, chemicals, and ammonia need 24/7 high-temperature heat that current renewables cannot deliver, and Nucor's investment is a tell. Isotope production — medical radioisotopes for PET scans, Tc-99m for diagnostic imaging — is a $10B+ market with chronic supply shortages that FRC reactors could address even before net electricity is proven. Space propulsion is the furthest adjacency; Helion's technology lineage overlaps with pulsed plasma thrusters, and a scaled-down FRC unit could be a credible deep-space propulsion program — Ad Astra Rocket and MSNW (Slough's other company) have worked in this space. The one adjacency that does not generalise is residential or small-commercial electricity: the regulatory and safety cost of fusion is too high for anything below utility scale, so the business model has to be centralised and hyperscaler-first.

Sources and further reading

Capital history

DateRoundAmountValuationLead(s)
2014-08 $1.5M — —
2015 ~$7M — —
2021-11 $500M (+ $1.7B milestone commitments) — —
2025-01 $425M — —

Investors / owners: Sam Altman, Mithril Capital, Nucor, Lightspeed Venture Partners, SoftBank Vision Fund 2, Y Combinator, Peter Thiel, Dustin Moskovitz

Competitive set

  • Commonwealth Fusion Systems —
  • TAE Technologies —
  • Tokamak Energy —
  • Zap Energy —
  • General Fusion —